[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"$fCeHU2THInSaISFpKDmbuitCUvbg8Q57tw4Wo3h0lCqU":3},{"id":4,"source":5,"question":6,"options":7,"answer":12,"related":13,"type":24,"origin":109,"createTime":26},102450718,"v1","下列哪项属于工程风险中的技术因素?()",[8,9,10,11],"自然灾害","工程设计理念的缺陷","施工质量缺陷","控制系统失灵",[],[14,27,37,47,57,67,77,85,95,99],{"id":15,"source":5,"question":16,"options":17,"answer":22,"related":23,"type":24,"origin":25,"createTime":26},102450697,"当工程风险产生的不利后果比较严重,又无其他策略可用时, 通过变更工程项目计划,从而消除风险本身或消除风险产生的条件,达到规避风险的目的.这种做法属于意外风险应对的哪种措施",[18,19,20,21],"风险转移","风险遏制","风险回避","风险化解",[],[],0,null,"2023-10-29T20:10:20+08:00",{"id":28,"source":5,"question":29,"options":30,"answer":35,"related":36,"type":24,"origin":25,"createTime":26},102450699,"当工程师发现所在的企业或公司进行的工程活动会对环境、社会和公众的人身安全产生危害时,应该及时地给予反映或揭发.这属于工程师的",[31,32,33,34],"职业伦理责任","社会伦理责任","个人伦理责任","法律责任",[],[],{"id":38,"source":5,"question":39,"options":40,"answer":45,"related":46,"type":24,"origin":25,"createTime":26},102450704,"对于可接受风险,以下哪种视角是专家视角()",[41,42,43,44],"可接受的风险是这样风险,在可以选择的情况下,伤害的风险至少相等于产生收益的可能性","可接受的风险指的是这样风险,它是通过行使自由和知情同意权而自愿认可的,或者它是得到适当赔偿的,并且它是公正地分配的","可接受的风险是这样风险,其保护公众免遭伤害的重要性远远超过了使公众获利的重要性","采取任何手段,只要让公众自愿接收的风险",[],[],{"id":48,"source":5,"question":49,"options":50,"answer":55,"related":56,"type":24,"origin":25,"createTime":26},102450706,"工程风险的伦理评估原则不包括",[51,52,53,54],"以人为本原则","预防为主","制度约束","经济至上",[],[],{"id":58,"source":5,"question":59,"options":60,"answer":65,"related":66,"type":24,"origin":25,"createTime":26},102450709,"下列不属于\"职业\"的特征是?()",[61,62,63,64],"理智性","长期性","自主性","非垄断性",[],[],{"id":68,"source":5,"question":69,"options":70,"answer":75,"related":76,"type":24,"origin":25,"createTime":26},102450713,"下列工程风险的伦理评估原则中哪项属于预防为主的原则",[71,72,73,74],"尊重当事人的\"知情同意\"权","要加强安全知识教育,提升人们的安全意识","考虑对社会环境和生态环境造成的影响","建立并落实安全生产问责机制",[],[],{"id":78,"source":5,"question":79,"options":80,"answer":83,"related":84,"type":24,"origin":25,"createTime":26},102450716,"下列哪项不属于工程伦理责任类型?()",[31,32,81,82],"环境伦理责任","家庭伦理责任",[],[],{"id":86,"source":5,"question":87,"options":88,"answer":93,"related":94,"type":24,"origin":25,"createTime":26},102450717,"下列哪项超出了工程伦理责任类型?()",[89,90,91,92],"过失-责任","赔偿-责任","角色-责任","义务-责任",[],[],{"id":4,"source":5,"question":6,"options":96,"answer":97,"related":98,"type":24,"origin":25,"createTime":26},[8,9,10,11],[],[],{"id":100,"source":5,"question":101,"options":102,"answer":107,"related":108,"type":24,"origin":25,"createTime":26},102450720,"下列属于工程风险的外部评估主体的是()",[103,104,105,106],"工程师","社会公众","工人","管理者",[],[],{"courseName":110,"courseImg":111,"workName":112,"workId":113,"count":114,"courseId":115},"工程伦理（电子信息）","https:\u002F\u002Ftihai-oss-cloud.itihey.com\u002Fimg\u002Ffb4e0e6a5574c0a2bea5a3691ff957f7.jpg","2工程风险安全责任","163b96d6fc8048189d8abdf699094c1c",74,"254901436f049b7821bf0f9db5bbe596"]