[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"$fauKDc52SsWJlY2leNN6CxN7ZHQuW8mJuxvFCFdu5mYc":3},{"answer":4,"createTime":5,"id":6,"options":7,"origin":12,"question":16,"related":17,"source":27,"type":28},[],"2023-12-25 17:56:02",121400351,[8,9,10,11],"同一时间段只能有一个专业队投入流水施工","由一个专业队在各施工段上依次施工","各专业队按施工顺序应连续、均衡地组织施工","施工现场的组织管理简单,工期最短",{"courseId":13,"courseImg":14,"courseName":15},"0628686293eb700b408f58093e51ce63","https:\u002F\u002Ftihai-oss-cloud.itihey.com\u002Fimg\u002F56f3e7a2de11d99f886fc57dafcc9547.jpg","建设工程项目管理（第七期）","建设工程组织流水施工时,其特点之一是( )",[18,29,38,43,46,55,62,71,76,85],{"answer":19,"createTime":5,"id":20,"options":21,"question":26,"source":27,"type":28},[],121400335,[22,23,24,25],"斜道图","横道图","网络图","施工平面图","在时间坐标中用横的线段表示各施工过程的开始、结束及延续时间,同时反映各施工过程相互关系的指示图表称为( )","v1",0,{"answer":30,"createTime":5,"id":31,"options":32,"question":37,"source":27,"type":28},[],121400341,[33,34,35,36],"流水施工","平行施工","依次施工","搭接施工","组织施工几种方式中,施工工期最短,一次性投入的资源量最集中的方式是( )",{"answer":39,"createTime":5,"id":40,"options":41,"question":42,"source":27,"type":28},[],121400347,[35,34,33,36],"采用( )组织方式,施工现场的组织管理简单,日资源用量少,工期长",{"answer":44,"createTime":5,"id":6,"options":45,"question":16,"source":27,"type":28},[],[8,9,10,11],{"answer":47,"createTime":5,"id":48,"options":49,"question":54,"source":27,"type":28},[],121400357,[50,51,52,53],"流水步距","组织间歇","流水节拍","平行搭接时间","( )数值大小,可以反映流水速度快慢、资源供应量大小",{"answer":56,"createTime":5,"id":57,"options":58,"question":61,"source":27,"type":28},[],121400359,[52,50,59,60],"施工过程数","流水段数","下列流水参数中属于空间参数的是( )",{"answer":63,"createTime":5,"id":64,"options":65,"question":70,"source":27,"type":28},[],121400363,[66,67,68,69],"工艺参数","空间参数","时间参数","组织参数","在组织流水施工时,用以表达流水施工在施工上开展顺序及其特征的参数,称为( )",{"answer":72,"createTime":5,"id":73,"options":74,"question":75,"source":27,"type":28},[],121400366,[66,67,68,69],"( )一般指的是在组织拟建工程流水施工时,其整个建造过程可分解的几个施工步骤",{"answer":77,"createTime":5,"id":78,"options":79,"question":84,"source":27,"type":28},[],121400368,[80,81,82,83],"确定最低限度人数","确定最高限度人数","确定最可能人数","确定最合理人数","确定某一施工过程所需安排的施工班组人数时,考虑&quot;最小工作面&quot;是为了( )",{"answer":86,"createTime":5,"id":87,"options":88,"question":89,"source":27,"type":28},[],121400370,[52,50,59,60],"相邻两个施工班组投入施工的时间间隔称为( )"]