[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"$f_XZ3EV_teEdDWT6TDquaFZx-dSmyErGyC5NZgFka2ik":3},{"id":4,"source":5,"question":6,"options":7,"answer":12,"related":13,"type":24,"origin":100,"createTime":37},143836799,"v1","自由时差,是各项工作在不影响紧后工作( )时间的条件下所具有的机动时间",[8,9,10,11],"最早开始","最迟开始","最迟结束","最早结束",[],[14,27,38,48,57,67,71,77,82,90],{"id":15,"source":5,"question":16,"options":17,"answer":22,"related":23,"type":24,"origin":25,"createTime":26},143836793,"某工程网络计划中工作M 的总时差和自由时差分别为5天和3天,该计划执行过程中经检查发现只有工作M的实际进度拖后4天,则工作M 的实际进度( )",[18,19,20,21],"既不影响总工期,也不影响其后续工作的正常执行","不影响总工期,但使其紧后工作的最早开始时间推迟1天","将其紧后工作的最早开始时间推迟1天,并使总工期延长1天","不影响其后续工作的继续进行,但使总工期延长1天",[],[],0,null,"2024-05-15T21:15:32+08:00",{"id":28,"source":5,"question":29,"options":30,"answer":35,"related":36,"type":24,"origin":25,"createTime":37},143836794,"双代号网络中只有内向箭线无外向箭线段的结点是( )",[31,32,33,34],"结束结点","起始结点","任意结点","中间结点",[],[],"2024-05-15T21:15:33+08:00",{"id":39,"source":5,"question":40,"options":41,"answer":46,"related":47,"type":24,"origin":25,"createTime":37},143836795,"已知在工程网络计划中,某工作有四项紧后工作,它们的最迟开始时间分别为第18天、第20天、第21天和第23天.如果该工作的持续时间为6天,则其最迟开始时间为( )天",[42,43,44,45],"17","12","15","14",[],[],{"id":49,"source":5,"question":50,"options":51,"answer":55,"related":56,"type":24,"origin":25,"createTime":37},143836796,"如果A、B两项工作的最早开始时间分别为第6天和第7天,它们的持续时间分别为4天和5天,则它们共同紧后工作C的最早开始时间为第( )天",[52,43,53,54],"10","11","13",[],[],{"id":58,"source":5,"question":59,"options":60,"answer":65,"related":66,"type":24,"origin":25,"createTime":37},143836797,"在网络计划中,关键工作的总时差值为( )",[61,62,63,64],"不定数","最大","最小","零",[],[],{"id":4,"source":5,"question":6,"options":68,"answer":69,"related":70,"type":24,"origin":25,"createTime":37},[8,9,10,11],[],[],{"id":72,"source":5,"question":73,"options":74,"answer":75,"related":76,"type":24,"origin":25,"createTime":37},143836801,"双代号网络中既有外向箭线又有内向箭线段的结点是( )",[34,33,32,31],[],[],{"id":78,"source":5,"question":59,"options":79,"answer":80,"related":81,"type":24,"origin":25,"createTime":37},143836803,[62,63],[],[],{"id":83,"source":5,"question":84,"options":85,"answer":88,"related":89,"type":24,"origin":25,"createTime":37},143836805,"某工程网络计划中,C工作的总时差为8d,自由时差为5d,在检查实际进度时,发现C工作的持续时间延长了6d,则说明c工作的实际进度将使其紧后工作的最早开始时间推( )",[86,87],"1d,但不影响总工期","1d,同时使总工期延长2d",[],[],{"id":91,"source":5,"question":92,"options":93,"answer":98,"related":99,"type":24,"origin":25,"createTime":37},143836807,"前锋线比较法适用施工进度计划用( )表达",[94,95,96,97],"横道图","单代号网络图","双代号网络图","时标网络图",[],[],{"courseName":101,"courseImg":102,"workName":103,"workId":104,"count":105,"courseId":106},"工程项目管理","https:\u002F\u002Ftihai-oss-cloud.itihey.com\u002Fimg\u002F1a188d99652843d3a275a7a512e5b2b2.jpg","23年秋习概论第六章推动高质量发展","work_35047387",45,"a912e7a29b2a127c02ed61b57485a34b"]