[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"$fH7Vx6YR1u9Zwx6dmuueYXZBHYLXrZun6LH0tQGvKh_w":3},{"id":4,"source":5,"question":6,"options":7,"answer":12,"related":13,"type":24,"origin":41,"createTime":26},203716914,"v1","对于下述施工阶段投资控制的工作流程中,排在最后一步应该是( )",[8,9,10,11],"审核索赔文件","签证索赔文件","审核已完工程实物量","将实际投资与计划投资进行比较",[],[14,27,31],{"id":15,"source":5,"question":16,"options":17,"answer":22,"related":23,"type":24,"origin":25,"createTime":26},203716908,"建设工程实际投资,即人力、物力、财力的输入主要发生在( )阶段",[18,19,20,21],"可行性研究阶段","立项阶段","设计阶段","施工阶段",[],[],0,null,"2025-06-18T13:22:54+08:00",{"id":4,"source":5,"question":6,"options":28,"answer":29,"related":30,"type":24,"origin":25,"createTime":26},[8,9,10,11],[],[],{"id":32,"source":5,"question":33,"options":34,"answer":39,"related":40,"type":24,"origin":25,"createTime":26},203716919,"投资目标的分析方法有( )",[35,36,37,38],"按投资构成、按子项目或按时间分解","按投资资金、按子项目或按时间分解","按投资构成、按项目或按时间分解","按投资构成、按项目或按空间分解",[],[],{"courseName":42,"courseImg":43,"workName":44,"workId":45,"count":46,"courseId":47},"建设工程监理概论","https:\u002F\u002Ftihai-oss-cloud.itihey.com\u002Fimg\u002Fbf09e2e59803d52b7a3052e785a504dc.jpg","随堂作业6-2.1","work_40732942",3,"26bbaf9eb709e8efbb03eab4f45dfabc"]