[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"$fFgs3d7NfGO4pB2gUSrS9wp5vkWFXN8gbaJMaogZy3TI":3},{"id":4,"source":5,"question":6,"options":7,"answer":12,"related":13,"type":24,"origin":110,"createTime":26},291746755,"v1","预制构件生产的通用工艺流程,正确的顺序为:( )",[8,9,10,11],"模台清理--模具组装--钢筋加工安装--管线、预埋件等安装--混凝土 浇筑--养护--脱模--表面处理--运输存放--成品验收","模台清理--模具组装--钢筋加工安装--管线、预埋件等安装--混凝土 浇筑--养护--脱模--表面处理--成品验收--运输存放","模台清理--模具组装--混凝土浇筑--钢筋加工安装--管线、预埋件等 安装--养护--表面处理--脱模--成品验收--运输存放","模台清理--模具组装--钢筋加工安装--管线、预埋件等安装--混凝土 浇筑--养护--表面处理--脱模--成品验收--运输存放",[],[14,27,37,47,57,67,77,86,96,106],{"id":15,"source":5,"question":16,"options":17,"answer":22,"related":23,"type":24,"origin":25,"createTime":26},291746746,"《装配式混凝土结构技术规程》JGJ 1-2014 规定,放架堆放或运输墙板时, 构件与地面倾斜角度宜大于( )度",[18,19,20,21],"30","80","45","60",[],[],0,null,"2025-12-29T08:10:13+08:00",{"id":28,"source":5,"question":29,"options":30,"answer":35,"related":36,"type":24,"origin":25,"createTime":26},291746747,"下列说法正确的是( )",[31,32,33,34],"装配式高层建筑含精装修可在半年内完成(错误答案)","装配式建筑不能完全解决传统建筑方式普遍存在的\"质量通病\"","装配式建筑的一大变革是将农民工变成操作工人","装配式建筑的现场用人少,时间短,综合成本降低",[],[],{"id":38,"source":5,"question":39,"options":40,"answer":45,"related":46,"type":24,"origin":25,"createTime":26},291746748,"当构件翻身强度不得低于 ( ),经过复核满足翻身和吊装要求时,允许将 构件翻身和起吊",[41,42,43,44],"设计强度的大于 C15,低于 70%","以上说法都不正确","设计强度的 70%且不低于 C20","设计强度的 30%并不低于 C15",[],[],{"id":48,"source":5,"question":49,"options":50,"answer":55,"related":56,"type":24,"origin":25,"createTime":26},291746749,"关于预制剪力墙、柱的安装叙述不正确的是( )",[51,52,53,54],"下一层预制剪力墙墙、柱的竖向预留钢筋插入预制剪力墙、柱底部的套筒中, 定向入座后,立即加设不少于 2 根的斜支撑对预制剪力墙、柱临时固定","斜支撑与楼面的水平夹角不应小于 60゜","在预制剪力墙安装施工层配置一名信号工和四名吊装工","在吊装工的指挥下,塔吊将预制剪力墙、柱下落至设计安装位置",[],[],{"id":58,"source":5,"question":59,"options":60,"answer":65,"related":66,"type":24,"origin":25,"createTime":26},291746750,"我国装配式建筑发展大力推行 EPC 管理模式,其中 EPC 指的是( )",[61,62,63,64],"施工装配一体化","项目总承包","工程总承包","设计标准化",[],[],{"id":68,"source":5,"question":69,"options":70,"answer":75,"related":76,"type":24,"origin":25,"createTime":26},291746751,"预制构件和部品经检查合格后,宜设置( ).预制构件和部品出厂时,应出 具质量证明文件",[71,72,73,74],"存放标识","工序标识","合格证","表面标识",[],[],{"id":78,"source":5,"question":79,"options":80,"answer":84,"related":85,"type":24,"origin":25,"createTime":26},291746752,"灌浆料在标准温度和湿度条件下,1d 的抗压强度要求为≥( )Mpa",[81,21,82,83],"75","85","35",[],[],{"id":87,"source":5,"question":88,"options":89,"answer":94,"related":95,"type":24,"origin":25,"createTime":26},291746753,"安装预制墙板、预制柱等竖向构件时,应采用可调( )临时固定;支撑的 位置应避免与模板支架、相邻支撑冲突",[90,91,92,93],"竖支撑","横支撑","剪刀撑","斜支撑",[],[],{"id":97,"source":5,"question":98,"options":99,"answer":104,"related":105,"type":24,"origin":25,"createTime":26},291746754,"《钢筋套筒灌浆连接应用技术规程》JGJ 355-2015 中规定现浇结构施工后 外露连接钢筋的中心位置允许偏差为( )mm",[100,101,102,103],"-5~0","0~+5","0~+3","-3~0",[],[],{"id":4,"source":5,"question":6,"options":107,"answer":108,"related":109,"type":24,"origin":25,"createTime":26},[8,9,10,11],[],[],{"courseName":111,"courseImg":112,"workName":113,"workId":113,"count":24,"courseId":114},"默认课程","https:\u002F\u002Ftihai-oss-cloud.itihey.com\u002Fimg\u002F03a579384a6dc297c89809b582fcc767.png","","53e1d2ef4961cca8eea3e23969ad2cb9"]