[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"$fzRd0JCoBTZffdh0B5_m3VMDclcOjcRDrYbjDFY0YLPk":3},{"answer":4,"createTime":5,"id":6,"options":7,"origin":12,"question":16,"related":17,"source":27,"type":28},[],"2026-01-26 14:43:26",317057470,[8,9,10,11],"关键工作的自由时差为零","相邻两项关键工作之间的时间间隔为零","关键工作的持续时间最长","关键工作的最早开始时间与最迟开始时间相等",{"courseId":13,"courseImg":14,"courseName":15},"53e1d2ef4961cca8eea3e23969ad2cb9","https:\u002F\u002Ftihai-oss-cloud.itihey.com\u002Fimg\u002F03a579384a6dc297c89809b582fcc767.png","默认课程","当双代号网络计划的计算工期等于计划工期时,对关键工作的错误提法是()",[18,29,38,47,56,65,74,83,92,95],{"answer":19,"createTime":5,"id":20,"options":21,"question":26,"source":27,"type":28},[],317057462,[22,23,24,25],"影响工程总工期","变为关键工作","影响其紧后工作的最早开始时间","不影响其后续工作的计划安排","在工程网络计划执行过程中,如果只发现工作Р进度出现拖延,且拖延的时间已超过原进度计划中该工作的自由时差,则工作P将()","v1",0,{"answer":30,"createTime":5,"id":31,"options":32,"question":37,"source":27,"type":28},[],317057463,[33,34,35,36],"减少关键工作的总时差","缩短关键工作的持续时间","减少工作的自由时差","缩短相邻工作之间的时间间隔","当工程网络计划的计算工期大于要求工期时,为满足要求工期,对网络计划进行调整的基本方法是()",{"answer":39,"createTime":5,"id":40,"options":41,"question":46,"source":27,"type":28},[],317057464,[42,43,44,45],"设计单位","监理工程师","业主","主管部门","对于工程中所用的主要材料和设备,在订货之前施工单位应进行申报,经()同意后方可订货",{"answer":48,"createTime":5,"id":49,"options":50,"question":55,"source":27,"type":28},[],317057465,[51,52,53,54],"基层处理不符合质量要求","对板材质量的检验不严格","镶贴前试拼不认真","施工操作不当,特别是分次灌浆时,灌浆高度过低","大理石墙、柱面饰面接缝不平、板面纹理不顺、色泽不匀的原因分析错误的是()",{"answer":57,"createTime":5,"id":58,"options":59,"question":64,"source":27,"type":28},[],317057466,[60,61,62,63],"公司、项目、班组","企业、工区、施工队","企业、公司、工程处","工区、施工队、班组","对建设工程来说,新员工上岗前的三级安全教育具体应由()实施",{"answer":66,"createTime":5,"id":67,"options":68,"question":73,"source":27,"type":28},[],317057467,[69,70,71,72],"决策能力","质量意识","安全意识","大局观能力","人的因素对建设工程项目质量形成的影响是指直接履行建设工程项目质量职能的决策者、管理者和作业者个人的()量活动能力",{"answer":75,"createTime":5,"id":76,"options":77,"question":82,"source":27,"type":28},[],317057468,[78,79,80,81],"分包单位负责人","总包单位总工程师","施工技术人员","总包单位负责人","施工组织总设计是由()编制",{"answer":84,"createTime":5,"id":85,"options":86,"question":91,"source":27,"type":28},[],317057469,[87,88,89,90],"不是同批涂料,颜料掺量有差异","使用涂料时未搅拌匀或任意加水,使涂料本身颜色深浅不同,造成墙面颜色不均匀","基层材料差异,混凝土或砂浆龄期相差悬殊,湿度、碱度有明显差异","喷涂骨架层时,骨料稠度改变;空压机压力变化过大;喷嘴距基层距离、角度变化及喷涂快慢不匀等都会造成花纹大小不一致","下列不属于内墙和顶棚涂料涂层颜色不均匀原因分析的是()",{"answer":93,"createTime":5,"id":6,"options":94,"question":16,"source":27,"type":28},[],[8,9,10,11],{"answer":96,"createTime":5,"id":97,"options":98,"question":103,"source":27,"type":28},[],317057471,[99,100,101,102],"对轻钢龙骨的力学性能能进行复验","对人造木板的甲醛释放量进行复验","对纸面石膏板的放射性进行复验","对膨胀螺栓的抗拉拔性能进行复验","下列关于吊顶材料复验的说法正确的是()"]