[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"$f-jmBeSjrmjQR_SGshSMnJGo05a9Y-BvKu-fYJ0tZ4s8":3},{"id":4,"source":5,"question":6,"options":7,"answer":10,"related":11,"type":18,"origin":104,"createTime":20},1071165379,"v2","当某项工作的拖延超过了它拥有的总时差,就必然造成紧后工作最早开始时间的延误.( )",[8,9],"对","错",[],[12,21,32,42,46,56,63,73,84,93],{"id":13,"source":5,"question":14,"options":15,"answer":16,"related":17,"type":18,"origin":19,"createTime":20},1071165340,"当某项工作的延误超过了它拥有的自由时差,就必然会造成总工期的拖延. ( )",[8,9],[],[],3,null,"2025-12-31T09:09:57+08:00",{"id":22,"source":5,"question":23,"options":24,"answer":29,"related":30,"type":31,"origin":19,"createTime":20},1071165356,"分部分项工程施工组织设计以( )为编制对象",[25,26,27,28],"单位工程","分部(分项)工程","专业工程","工程项目",[],[],0,{"id":33,"source":5,"question":34,"options":35,"answer":40,"related":41,"type":31,"origin":19,"createTime":20},1071165366,"下列( )工程属于单项工程",[36,37,38,39],"一个钢铁厂","学校教学楼","工业管道工程","基础工程",[],[],{"id":4,"source":5,"question":6,"options":43,"answer":44,"related":45,"type":18,"origin":19,"createTime":20},[8,9],[],[],{"id":47,"source":5,"question":48,"options":49,"answer":54,"related":55,"type":31,"origin":19,"createTime":20},1071165395,"网络图是由( )组织的,用来表示工作流程的有向.有序网状图形",[50,51,52,53],"节点和线路","线路和关键线路","箭线和节点","虚箭线和节点",[],[],{"id":57,"source":5,"question":58,"options":59,"answer":61,"related":62,"type":31,"origin":19,"createTime":20},1071165414,"下列( )工程属于分项工程",[60,37,38,39],"砖砌基础",[],[],{"id":64,"source":5,"question":65,"options":66,"answer":71,"related":72,"type":31,"origin":19,"createTime":20},1071165432,"如果施工段不变,若流水节拍越大,则流水步距( )",[67,68,69,70],"越小","不变","越大","不能确定",[],[],{"id":74,"source":5,"question":75,"options":76,"answer":81,"related":82,"type":83,"origin":19,"createTime":20},1071165441,"物资准备包括( )",[77,78,79,80],"材料准备","施工机具","场地准备","运输准备",[],[],1,{"id":85,"source":5,"question":86,"options":87,"answer":91,"related":92,"type":31,"origin":19,"createTime":20},1071165445,"( )是建设项目最小的组成部分",[25,88,89,90],"分部工程","检验批","分项工程",[],[],{"id":94,"source":5,"question":95,"options":96,"answer":102,"related":103,"type":83,"origin":19,"createTime":20},1071165459,"施工单位现场准备工作的内容包括( )",[97,98,99,100,101],"清除障碍物","做好七通一平","测量放线","搭设临时设施","施工物资准备",[],[],{"courseName":105,"courseImg":106,"workName":107,"workId":107,"count":31,"courseId":108},"[共享课]建筑施工组织设计","https:\u002F\u002Ftihai-oss-cloud.itihey.com\u002Fimg\u002F986abfa7885cbaf30797873be3b3956a.png","","1000101418"]