单选题 A new project being considered by BLWCo would require 1,000 hours of skilled labour.The current workforce is already fully employed but more workers can be hired in at a cost of $20 per hour.The current workers are paid $15 per hour on a project that earns a contribution of S10 per hour.What is the relevant cost of labour to be included in the project appraisal
A. $10,000
B. $15,000
C. $20,000
D. $25,000(2 marks)