单选题 You priced out a project at 1,000 hours assuming a grade 7 employee would be assigned. The functional manager assigns a grade 9 employee. This will result in a great cost overrun. The project manager should ( )

A. Reschedule the start date of the project based on the availability of a grade 7

B. Ask the sponsor for a higher priority for your project

C. Reduce the scope of the project

D. See if the grade 9 can do the job in less time