单选题 双代号网络计划中,虚工作的作用是( ). In the activity-on-arrow network plan, the role of dummy activity is to ( )
A. Correctly express the interval between two activities
B. Correctly express the duration of related activities
C. Correctly express the free float of related activities
D. Correctly express the logical relationships between related activities

学科:Construction Organization and Schedule Management 施工组织与进度管理