单选题 双代号网络图中的虚工作是( ).The dummy activity in the activity-on-arrow network diagram ( )
A. Consumes both time and resources
B. Only consumes time, not resources
C. Consumes neither time nor resources
D. Consumes only resources, not time

学科:Construction Organization and Schedule Management 施工组织与进度管理
时间:2024-07-05 16:12:20