单选题 在网络计划中,工作的最早开始时间应为其所有紧前工作( ).In the network plan, the earliest start time of activity shall be ( ) for all its immediate predecessor activities

A. Maximum value of earliest finish times

B. Minimum value of earliest finish times

C. Maximum value of latest finish times

D. Minimum value of latest finish times