单选题 当工作具有多个紧前和紧后工作时,该工作的最迟完成时间( ).When an activity has multiple immediate predecessor and successor activities, the latest finish time of the activity is ( )
A. Maximum value of the latest finish times for all immediate successor activitie
B. Maximum value of earliest finish times for all immediate predecessor activities
C. Minimum value of the latest start times of all immediate successor activities
D. Minimum value of the latest finish times for all immediate successor activities

学科:Construction Organization and Schedule Management 施工组织与进度管理