题目详情
单选题 双代号网络计划中,只表示前后相邻工作的逻辑关系,既不占用时间,也不耗用资源的虚拟的工作称为( ).In the activity-on-arrow network plan, a virtual activity that only represents the logical relationship between adjacent activities without consuming time or resources is called ( )
A. Immediate predecessor activity
B. Immediate successor activity
C. Key activity
D. Dummy activity

学科:Construction Organization and Schedule Management 施工组织与进度管理
时间:2024-07-05 16:12:20