单选题 双代号网络计划中,只表示前后相邻工作的逻辑关系,既不占用时间,也不耗用资源的虚拟的工作称为( ).In the activity-on-arrow network plan, a virtual activity that only represents the logical relationship between adjacent activities without consuming time or resources is called ( )

A. Immediate predecessor activity

B. Immediate successor activity

C. Key activity

D. Dummy activity