题目详情
单选题 工作 E 有四项紧前工作 A、B、C、D,持续时间分别为:A=4、B=6、C=7、D=5,其最早开始时间分别为:A工作ES=8、B工作ES=6、C工作ES=6、D工作ES=10,则工作 B 的自由时差为( ).If activity E has four immediate predecessor activities A, B, C and D, with the duration of A=4, B=6, C=7 and D=5 respectively, and the earliest start time is ES=8 for activity A, ES=6 for activity B, ES=6 for activity C and ES=10 for activity D, so the free float of activity B is ( )

学科:Construction Organization and Schedule Management 施工组织与进度管理